NTPC Limited announced the declaration of Commercial Operation (COD) for the second and last part capacity of 52 MW out of 245 MW at Plot-3 of its Nokh Solar PV Project in Rajasthan.
The COD is effective from 00:00 Hrs. on 22 June 2025.
The first part capacity of 193 MW of the 245 MW project had already been declared commercially operational on 9 June 2025.
With this commissioning, NTPC's total standalone commercial capacity has reached 60,318 MW, and its group commercial capacity stands at 81,420 MW.
The total standalone installed capacity is now 60,978 MW, and the total group installed capacity is 82,080 MW.